Update on the MoPac Intersections – Slaughter Lane & La Crosse Ave

Slaughter Update

Over the coming weeks, crews expect to complete final paving, striping, and installing pedestrian crosswalks and signage at the Slaughter Lane intersection, weather and field conditions permitting.  A full two-day closure of Slaughter Lane at MoPac will be needed to safely and quickly complete these tasks.  More information be be provided as the work approaches.

Throughout other areas of the project, crews will continue working on curb and gutter installation, striping and placement of overhead signage.  Regular nightly lane closures are scheduled next week to allow crews to carry out/complete these activities.

Alternating Nightly Lane Closures

  • North and southbound MoPac
  • Aug 11-15 (Sunday-Thursday) 8 p.m.-6 a.m.
  • East and westbound Slaughter
  • Aug 12-15 (Monday-Thursday) 8 p.m.-6 a.m.
  • Aug 16 (Friday) 10:30 p.m-8:30 a.m.

Sincerely,

MoPac Intersections Project Team

(512) 693-7425

MoPacIntersections@txdot.gov

 


General Construction Information

Please note that schedules are subject to change due to weather or field conditions. General work hours take place Sunday through Friday. Work will occur both during the day and at night during the times shown below, unless otherwise noted.

Daytime Work Hours: 7 a.m. to 6 p.m.
Nighttime Work Hours: 7 p.m. to 6 a.m.

MoPac:

Alternating north and southbound lane closures continue nightly from South Bay Lane to Davis Lane.

Sunday – Thursday, 8 p.m. – 6 a.m.
Friday – Saturday, 10 p.m. – 8 a.m.

Slaughter:

Alternating east and westbound lane closures continue nightly at the MoPac intersection.

Sunday – Thursday, 9 p.m. – 5:30 a.m.
Friday – Saturday, 10:30 p.m. – 8 a.m.